The existing 22.5-meter caisson required a complete overhaul. Faced with the challenges of a harsh offshore environment and limited crane reach, our experts turned to innovative below-deck lifting and cross-haul techniques. This strategic approach not only ensured a seamless installation but also minimized disruption to ongoing operations.
The new caisson, divided into two parts yet maintaining the same total length, now features an enhanced intermediate spool for increased stability. Our skilled team of five experts, proficient in rope access and mechanical work, executed this complex project safely and on schedule, exceeding client expectations.
This successful caisson replacement is a testament to our commitment to operational integrity and our ability to tackle even the toughest offshore challenges.